Lake Zurich will construct a noise wall to protect some
homeowners, using more than $500,000 received from Canadian National Railway
through a legal settlement.
CN provided nearly $2 million to Lake Zurich for safety
upgrades, noise reduction and other measures deemed necessary because of an
expected increase in freight trains the company runs through the village. The
federal Surface Transportation Board ordered CN to reduce train noise in certain
areas.
As part of the process involved with spending CN's cash,
Lake Zurich officials received feedback from residents in affected neighborhoods
on what they preferred in the way of noise protection.
Residents on Carolyn Court, just north of where East Main
Street meets Route 22, expressed a preference for the noise wall. By a 5-0 vote,
village trustees at a recent meeting agreed to pay $522,263 to the lowest
responsible bidder, Woodstock-based Alliance Contractors Inc., for the barrier
construction.
Although Alliance doesn't have specific noise wall
construction experience, it's been deemed qualified to do the job in Lake
Zurich, according to Mark Johnson, project manager with village engineering
consultant Ciorba Group of Chicago. Alliance's specialties include work on
retaining walls, sidewalks, bridges and box culverts.
Some concern about the tab was raised by Trustee Tom
Poynton, who said he didn't want too much of CN's $1.9 million spent in one
place.
"Are we going to have enough money left in this (CN) fund
to do all the things that we told the people that we were going to do as far as
noise mitigation?" Poynton said.
Plans call for other CN money to go toward safety
mitigation work near schools, downtown Lake Zurich and other areas adjacent to
the company's tracks.
David Heyden, Lake Zurich's public works director and
village engineer, said in a memo that the 2010 agreement with CN required the
entire $1.9 million be allocated to projects within two years. The village has
formally requested a deadline extension to July based on the anticipated noise
wall construction schedule, Heyden said.
Last month, officials in neighboring Hawthorn Woods agreed
to use most of cash remaining from what it had received from the settlement to
ensure officials have electrical power to do their jobs in the event of a
crisis.
An amount not to exceed $43,000 will be used to buy and
install generators at the village hall and adjoining police department/emergency
operations center, a central location where village decision makers meet in the
event of a disaster that needs a coordinated response.
Hawthorn Woods received a $760,000 settlement in September
2009 when it dropped out of litigation involving the CN's acquisition of the
EJ&E.
No comments:
Post a Comment